Construction Progress

Project Overview

“Works are currently ongoing on the level one slab which will be completed later this month.

The retaining walls and lift core is completed from level one to level two and the falsework and formwork is ongoing.

The formwork is completed from the ground floor to level one and the slab will be poured in the next two weeks.” – Stephen Bush
January 11, 2019

Stephen Bush is our Project Manager with more than 30 years of experience and a proven track record of success in delivering multi-million-dollar projects. His academic background includes a Bachelor of Engineering Degree in Civil and Structural Engineering from Bradford University in England and early in his career, he served as Lieutenant in the Corps of Royal Engineers for 3 years and attended Royal Military Academy Sandhurst as well as the Royal School of Military Engineering.

On completion of his commission he entered the Construction Industry working for major construction companies in England projects included the Channel tunnel and the second tallest building in England on Canary Wharf in London.  He moved overseas in 1993 during his time overseas he has held senior operational and project management roles in Vietnam, Malaysia, UAE, Saudi Arabia, Germany, Trinidad, Mauritius, Myanmar and now we are pleased to have him with us in Sri Lanka.

Previous Construction update Videos

29th November 2018 – 11th January 2018

07th November 2018 – 29th November 2018

19th October 2018 – 07th November 2018

26th September 2018 – 19th October 2018

12th September 2018 – 26th September 2018

28th August 2018 – 12th Septmeber 2018

06th August 2018 – 28th August 2018

23rd July 2018 – 6th August 2018

29th June 2018 – 23rd June 2018

8th June 2018 – 29th June 2018

28th May 2018 – 8th June 2018

26th April 2018 – 28th May 2018

20th April 2018 – 26th April 2018

Construction Timelapse